Significant progress achieved in Sokoria 30 MW geothermal power project

2017/11/15

According to news from construction site, during the third quarter Kaishan’s geothermal power project in Sokoria Indonesia finished construction of production wells pads and construction of roads within the site. The first production well started drilling in October and has by now reached to the permeable layer. Preliminary temperature testing finds a temperature above 240 degrees. Based on the parameters gained from drilling, the capacity of the well is 6—8MW. According to project schedule, the official testing will be carried out in December.